Technology Standard
|
|
VCCS IT Communications
Plan |
Version: 2.0
Status: Approved: 02/01/08
Contact: Director Technology Services
PURPOSE
Scheduled or unscheduled outages of information technology(IT) services and infrastructure on a community college campus or at the System Office can and do impact the IT service delivery at other campuses, community colleges, and for those customers who may be accessing the services from an off campus location. An outage may have a short duration; however there are situations that could cause an outage to last for an extended time period. The primary concern is how best to communicate information regarding the outage in a way that permits those who are dependent on the services to receive current and accurate information for their decision making. This document outlines planning activities and related actions to be taken to ensure consistent communications in the event of a scheduled or unscheduled outage that impacts critical IT services.
SCOPE
This document addresses planning and actions to be taken at the System Office, colleges, campuses, and all VCCS off campus locations.
APPLICABILITY
This standard is applicable to the System Office and the twenty three community colleges.
EXPECTATIONS
It is expected that these recommendations will be implemented by the System Office and the Colleges and fully operational within one year of the approval of this standard assuming required funding and related resources are made available.
STANDARD
This document describes actions to be taken by College and/or System Office personnel in the event of an unexpected or anticipated major outage or interruption of IT services such as the failure of a primary network circuit, loss of the Internet connection, or extensive damage to the physical facilities. Such an outage could be caused by human error or an unexpected natural disaster that would force a closure and/or put the operations at risk due to potential power outages. Similarly, if any VCCS location experiences or anticipates any type of major outage or interruption in IT services that will impact the VCCS Intranet or delivery of services to colleges then this Plan is to be invoked.
All VCCS locations
have an internal network infrastructure as well as a high speed connection to
the VCCS primary network for the delivery of key IT services including voice
services. The System Office also provides system wide access to all enterprise
applications and services using the same primary network. Since an unexpected outage to network services
at any VCCS location, whether on a campus or on the backbone, could adversely
impact the performance or service delivery at or to other VCCS locations. Therefore each college and the System Office
must be prepared not only to maintain the local operations, but also work in a
coordinated fashion with the other colleges and the System Office to maintain
the IT service delivery for VCCS.
Note: This standard assumes that both the Colleges and System Office have fully complied with COV ITRM Standard SEC501 01.
PREPARATION
Colleges and the System Office should prepare in advance for system, network and infrastructure failures and interruptions by taking the following actions:
1.
All VCCS locations
should have a current disaster preparedness and recovery plan. This plan should
identify key components, key personnel, and actions to be taken in various
eventualities. In particular, it should address backup and recovery, and
procedures to be followed in the event of major storms or power outages. A
contact procedure should be developed and documented, so that Campus security,
facilities, and both the college and Information Technology Services (ITS) at
the System Office personnel can contact each other and can be contacted by the college
senior administrative staff.
2.
Colleges and the
System Office should be prepared to restore their web presence at an alternate
location to ensure that students, faculty, staff and other stakeholders are
kept informed during a disaster or other circumstance that causes primary IT
services and applications to be unavailable.
If a location does not have the capacity to restore their entire web
presence quickly, a single web page with announcements and links to enterprise
resources should be made available in the interim. Locations that maintain their own DNS servers
should also take steps to ensure that DNS records can be changed quickly, even
if their primary data center is destroyed or otherwise unavailable. The ITS Enterprise Services at the System
Office will work with colleges to provide guidance and assistance where
necessary.
3.
The local network
should be made as resilient as possible utilizing UPS and generator resources whenever
possible. These units should be sized to cover at least the brief interruptions
that may occur during a normal summer thunderstorm. The servers should be
configured to perform a normal, controlled, shut down should the power outage
extend beyond the capacity of the UPS. At a minimum, the primary network edge
equipment, currently the edge router, firewall and voice gateway should be protected
by an UPS with a two to four hour capability.
4.
All VCCS locations should
provide ITS Client Services at the System Office with a list of key contacts,
including home phone numbers, pager numbers, and cell phone numbers in case
problems occur during off hours which require the System Office ITS Client
Services to contact the appropriate personnel. These numbers can either
be the direct numbers of the personnel themselves or the numbers for an Office who in turn should be able to notify the
appropriate staff.
5.
All VCCS locations
should implement the standard automated problem management software so
incidents can be tracked and managed by the System Office ITS Client Services.
6.
VCCS locations connected
to the MPLS Backbone side of the VCCS primary network should have at a minimum two
individuals with access to the network provider customer care center for
entering trouble tickets.
PRE- CLOSING ACTIONS
Should an
outage be anticipated due to a predicted major storm, or any other reason, the appropriate
personnel should contact the System Office ITS Client Services, informing them
of the locations plans. The location could make one of two choices:
1.
Close as appropriate,
but allow the local network and primary network equipment to stay on line. In
this case, the System Office ITS personnel will monitor the status of the location’s
primary network equipment.
2.
In coordination with
the System Office ITS personnel, take down the location’s network and primary
network equipment and establish the alternative web site presence.
Should
the outage occur unexpectedly, the appropriate College personnel should contact
the System Office ITS Client Services, if possible, to inform them of the
situation and to coordinate planning to restore network services.
DURING OUTAGE OR CLOSING
During
the time the location is closed, the safety of personnel is the primary concern.
Nothing should be done that would put any personnel at any significant risk.
However key personnel should remain in contact with the System Office ITS Client
Services. As soon as the location can predict an opening time or the time the
services will be restored, the System Office ITS Client Services should be
informed.
RE-ESTABLISHING THE PRIMARY NETWORK CONNECTION
Once it
is safe to return to the location; and power, telephone, and other utilities
have been reestablished, or when it is otherwise feasible to restore the
network services; network and other information technology personnel working
with the System Office ITS staff should restore the network to a normal
operational status.
POST MORTEM
Once the location
is back in normal operations, the key people responsible for the shutdown
activities and the restoration of services should analyze the actions taken. They should also document in the problem
management incident what happened and make any necessary changes to their
disaster recovery plan. Comments from the System Office ITS staff and from on
and off campus users should be included in developing the post mortem report.
FAILSAFE PROCEDURES
In the event any location experiences or anticipates any type of outage or interruption of IT services that is adversely impacting the VCCS Intranet or IT services being provided to other colleges, the following Failsafe Procedures will be invoked.
1) Should a location detect that one of its circuits is unavailable; the appropriate IT staff should notify the System Office ITS Client Services either via email, problem management software or telephone. The appropriate IT staff should also open a ticket with the network provider.
a) If the location is connected via a T1 or DS3 circuit, the appropriate IT staff can open a trouble ticket using the network provider customer care center
b) If the location is connected via Ethernet, the appropriate IT staff can open a trouble ticket by calling the current service provider.
staff must be prepared to answer the following
questions that will be asked by the network provider technician:
·
Type of Data
Service reported
·
Circuit ID # and
Site Address
·
Description of
Trouble
·
Advise if
customer provided equipment has been checked (i.e. Power, Error Indications,
cabling, A/C)
·
Advise if
intrusive testing can be performed
·
Site Access
Information: Site Access Times and Site Contact Information
To provide the quickest resolution, staff must provide
an onsite Contact name and phone number in the case that a network provider Technician
has to come to the site to resolve the issue.
Failure to do so may delay the restoration of services.
The System Office ITS Network staff must be contacted
if the trouble ticket has to be escalated.
2) Should the System Office ITS Staff detect a campus circuit is down, the System Office ITS Network staff will try to contact the appropriate IT Staff at the location to confirm or notify them about the outage. ITS Network Staff will notify ITS Client Services and open a trouble ticket with network provider to start the process of resolving the issue.
a) In the event that a location’s staff can not be reached, ITS Network staff will open a trouble ticket but will not allow intrusive testing to be performed without confirmation from the appropriate IT staff.
b) The onsite staff must be contacted before network provider technicians can be dispatched for onsite testing if that is deemed necessary.
3) The System Office ITS Client Services will send out a broadcast email notifying everyone of the outage
a) When required, the System Office ITS Client Services will also take additional steps to notify users, such as posting a notice on MYVCCS and Blackboard web pages.
4) In the event a server is creating a system wide problem such as a compromised server attempting to infect other servers or network devices. The System Office ITS Network staff will attempt to contact the appropriate point of contact for the rogue site in an effort to get the appropriate staff to correct the situation. In the event System Office ITS Network staff cannot contact the appropriate staff to get the situation resolved at the local level, the System Office ITS Network staff, as deemed necessary to protect other locations and networks and with approval from the Vice Chancellor or Director Enterprise Services at the System Office, will quarantine the infected server so that normal operations may be restored to the rest of the network.
5) When the problem has been resolved, the System Office ITS Network staff will work with the appropriate staff to expeditiously reestablish connectivity for the site in question.
CONCLUSION
It is imperative that the network and related IT services remain available at all times serving as many customers as is possible. The standard outlined in this document provides the System with a means of ensuring that continuous uninterrupted VCCS primary network access and support is available to the majority of the VCCS customers under the most adverse conditions. Working together we can minimize the impact of a failure so that it affects as few customers as possible.