
Telecommunications Cabling and Electronics Specifications Guidelines
Contact: Ron Olton
Entrance Facilities
The ENTRANCE FACILITY consists of the various types of telecommunications network
cables that enter the building and continue to the ENTRANCE WIRING CLOSET. The ENTRANCE
FACILITY also includes manholes, conduits, pull boxes, trenches and the appropriate
termination and protection devices. Fiber optic cable and copper twisted pair cable will
be included in most building entrances. These cables may be brought to the building by
either of two methods, direct buried or underground.
Direct buried cable is placed below the earths surface by digging a trench or
plowing the cable into place with the use of special sub-soil type plows made specifically
for that purpose. Either plowing or trenching does not require the use of conduit. Direct
buried is the least expensive method when existing conduit is not available, but is not
practical when multiple cables are involved.
Underground cable utilizes conduit placed below the earths surface by trenching.
Underground conduit systems require manholes placed below ground to facilitate pulling
cables into the conduit and splicing of the underground cables.
- GENERAL:
- New or remodeled buildings on the campus will provide entrance conduits in the size and
quantity specified by this section of the standard. These conduits will extend beyond the
foundation to 1) nearest existing manhole 2) location of a proposed manhole to be placed
as a part of the building project or 3) to a point beyond landscaped and/or paved areas,
if the entrance will be direct buried.
- SIZE:
- Entrance conduit will be 4-inches inside diameter.
- TYPE:
- Entrance conduit will be galvanized steel through the foundation wall to a point
12-inches beyond the disturbed earth. Bends and sweeps will be galvanized steel. Other
sections may be type C PVC conduit.
- QUANTITY:
- A minimum of one 4-inch conduit plus one spare conduit will always be required. If fiber
cables are required, an additional conduit with a minimum of three inner ducts will be
required.
Additional conduits may be required to accommodate special purpose cables or
due to high copper cable pair requirements. The need for added ducts for high pair
requirements can be determined from Table -1.
| Table 1-1 |
| Copper Cable Pairs |
No of Conduits Required* |
| 6 to 900 |
One, 4-inch |
| 901 to 2100 |
Two, 4-inch |
| 2101 to 3600 |
Three, 4-inch |
| 3601 to 4800 |
Four, 4-inch |
| 4801 to 6000 |
Five, 4-inch |
| 6001 to 7200 |
Six, 4-inch |
(*) Does not include one spare conduit or one conduit with inner duct installed
- DEPTH:
- Entrance should be placed at a depth of 48-inches to the top of the duct, if possible.
When obstructions prevent placement at that depth, a minimum depth of 24-inches should be
maintained.
- SEPARATIONS:
- All conduits paralleling power and other foreign conduits and pipes carrying gas, water,
oil, or sewer will have a minimum separation of 12-inches of firm earth. This separation
may be reduced to 4- inches if the entrance conduit is completely encased in 4-inches of
concrete. Crossing separations may be treated in the same manner with the concrete
encasement extending a minimum of 3-feet either side of the crossing.
- BENDS:
- Bends in underground conduit are undesirable and are to be avoided. When required, bends
and sweeps will be limited to the equivalent of no more than two 90 bends and will be
encased in 4-inches of concrete.
- ENTRANCES:
- Conduits entering through a basement or foundation wall will be sloped so that water
will not run into the building. All conduits will be sealed until used and seals will be
restored around the cables entering the building to prevent the entrance of water, gases
and vermin.
- CONCRETE CAPS:
- All runs of underground conduit not encased in concrete from other causes will be capped
with a minimum of 4-inches of concrete.
- MANHOLES:
- When required manholes will be no less than 8-feet by 4-feet in size, they will be
pre-cast and installed on a minimum of 12-inches of sand. Manholes will be provided
complete with a permanent ladder, cable racks, grounding/bonding inserts, pulling eyes,
lid, ring, collars and a sump of at least 8- inches in diameter.
- PULL LINES:
- All conduit placed will have a minimum of one ¼- inch nylon rope in each duct and inner
duct to facilitate placing pulling lines.
- METAL SECTIONS:
- All galvanized steel sections will be reamed on the interior edges to remove burrs.
Bushings will be installed on all open ends.
- DIRECT BURIED:
- Cables placed by this method should be 36-inches deep and no less than 24-inches deep
when necessary to clear other obstructions. Separations from other obstacles are the same
as for underground conduit except the concrete should be placed as a divider when needed,
not as an encapsulant. Cables may be placed in the same trench as other utilities but must
be separated by a minimum of 12-inches of firm earth. See Figures 1- 1 and 1-2 for proper
placement.
FIGURE 1-1 FIGURE 1-2
Return to Specifications